Client: NEWMAP Edo State.
Location: Edo State
Area: 948 m2
Status: Completed
Condition: Subcontracted by Hartland
Completion: Feb., 2019
Client: NEWMAP Edo State.
Location: Edo State
Area: 948 m2
Status: Completed
Condition: Subcontracted by Hartland
Completion: Feb., 2019
Construction and installation of 948 cu.m gabion/renomatress basket check dams.
The site is one of the NEWMAP sites in Edo State which is designated to solve the problem of gully erosion and the emerging land degradation and environmental insecurity and aims to reduce vulnerability to soil erosion in targeted catchments in Edo State. The job was sub contracted to us by the main contractor (Hartland Nig Ltd).